Developmental phases

Upcoming

The project for new nuclear capacity at the Kozloduy NPP site follows a clearly planned sequence of stages, including planning and design procedures, regulatory approvals, engineering, investment decisions, construction and commissioning. Key preparatory and permitting activities are planned for 2026, while in the period 2027–2030 the focus shifts to technical design, contracting, infrastructure preparation and the start of construction. The next stage, between 2030 and 2036, envisages construction activities, followed by commissioning and licensing.

Project life cycle​

Иконка 2030 - 2036.

Construction activities

Иконка 2036.

Obtaining licenses

Иконка 2036 - 2038.

Commissioning

Иконка 2097.

Decommissioning/extension of the useful life of the nuclear power plant

Key milestones for 2026

Иконка Initial stage

Entry into force of the PUP – site No. 2

Иконка Nuclear Regulatory Agency

Submitting a request for a design permit for block 8


Issuance of design permit block 7


Site approval block 8


Planning permission block 8

Иконка Engineering

Submission of a notification to the EC for state aid for new nuclear capacities


Completion of an engineering contract

Иконка Environmental assessment

Decision under Art. 45 ASUNE for Unit 7


Submission of EIA report for Unit 8

Иконка Construction

Building permit under Art. 142 of the ZUT block 7

Иконка Notification

Submission of a notification to the EC under Article 41 of the Euratom Treaty

Key milestones for 2027 - 2030

Иконка Supporting infrastructure

Construction of supporting infrastructure necessary for the construction and operation of the NAM

Иконка Solutions

EC decision on eligibility for state aid for construction of new nuclear capacity


Final investment decision

Иконка Conclusion of contracts

Conclusion of contracts:

1. EPC договор с консорциума

2. Експортни банки

Иконка Technical design and estimates

Preparation of a technical design and an interim safety analysis report (MOAB)


EIA Decision for Unit 8


Decision under Art. 45 ASUNE for Unit 8

Иконка Building permit

Nuclear Regulatory Agency:

1. Одобряване на технически проект и МОАБ

2. Издаване на разрешение за строителство


Building permit under Art. 148 of the ZUT, block 8

Иконка First nuclear concrete

Casting of the first core concrete of Unit 7


Construction of new nuclear power plants

Chronology of the project for the construction of a new nuclear power plant at the Kozloduy NPP site„

Year 2025

December 2025

A procedure has been launched for the expropriation of land properties falling within the territory of Site No. 2. 

2025 – December 22

The PUP was approved by Order, and it enters into force on 08.01.2026.

2025 – December 9

The company submitted an application to the NRA with a complete set of documents for issuing an order to approve the selected site for the deployment of a nuclear facility - Unit 8.

2025 – October 27

The Chairman of the Nuclear Regulatory Agency issues Permit for determining the location (selection of a site) of a nuclear facility, which marked the beginning of the permitting and licensing regime for Unit 8.

2023 year

2023 – October 25

The Council of Ministers of the Republic of Bulgaria gives its consent in principle under Article 45, paragraph 1 of the Law on the Safe Use of Nuclear Energy for the construction of Unit 8 of the Kozloduy NPP. 

2020 year

2020 – February 21

The Chairman of the NRA approves the site selected by "Kozloduy NPP - New Builds" EAD for the location of a nuclear facility - nuclear power plant (Site No. 2).

2019 year

2019 - April 08

Based on an effective EIA Decision, an updated written request has been submitted to the NRA for issuing an order for approval of a selected site, within the meaning of Art. 33, para. 4 of the ASUNE.

2015

2015 - June 12

A written request submitted to the NRA for issuing an order for approval of a selected site, within the meaning of Art. 33, para. 4 of the ASUNE.

2015 – January 27

Decision on EIA No. 1-1/2015. The Minister of Environment and Water approves the implementation of an investment proposal for the construction of a new nuclear power plant of the latest generation on Site 2 of the Kozloduy NPP site„

2014 year

2014 - July 3

Independent verification of the results and assessments obtained during the study and determination of the location of a new nuclear power plant at the Kozloduy NPP site, carried out by the Bulgarian Academy of Sciences.

2014.

Activities to prepare the safety justification for the NAM "Preliminary Safety Analysis Report" have started.

2013

2013 - October 28

Site selection activities are being completed - Site 2 of the Specialized Technical Council has been selected.

2013 - August 26

The NRA issues to "Kozloduy NPP - New Builds" EAD a permit for determining the location (site selection) of a nuclear facility.

2012 year

2012 - August 27 - November 26

Launch of feasibility studies:

Feasibility study for the construction of a nuclear power plant

Survey and determination of the location of the proposed site for the construction of the NAM

Preparation of an EIA for the construction of a NAM

2012 - May 9

Registration of "Kozloduy NPP - New Builds" EAD in the Commercial Register at the Registry Agency.

2012 - April 11

Council of Ministers – granting consent in principle for the construction of a nuclear power plant at the Kozloduy site.